Gateway Conveyor

60 Ton Conveyor system fabricated for Anglo American – All steelwork was galvanised and guards powder coated.

The challenge CEC faced with this project was that the client needed the equipment in 5 weeks versus a standard fabrication time of 8 weeks.

CEC managed to achieve the requested delivery by working extended hours, double shifts and managing bottlenecks by careful allocation of resources .

Items were delivered ahead of schedule at the required quality and our client called it “A small miracle”.